Toyota Kirloskar Motor (TKM) today announced the ramp up of its annual production capacity to 2, 10,000 units.
- (1888PressRelease) March 18, 2011 - Bangalore - In line with TKM's increasing annual production capacity and in order to cater to the increase in demand for the Innova , Fortuner,Corolla Altis and the Etios , the company will ramp up production to 2,10,000 units.
The company recently announced its plans for the introduction of second shift production in April , reduction in takt time (production time per vehicle), production enhancement and postponement of the launch of hatchback Etios Liva from April to June 2011 - all reflecting the active measures taken to reduce the waiting period for the Etios.
Furthering these measures, the annual production capacity of the first plant currently manufacturing the Innova, Corolla Altis and Fortuner, will be increased from 80,000 units to 90,000 units in the third quarter of 2011. The second plant currently manufactures the Etios. To cater to the increasing demand for Etios and with a view to reduce the waiting period, the annual production capacity for the second plant will be raised from 70,000 to 1,20,000 units . The expansion will be carried out in a phased manner starting in July 2011, extending into the second quarter of 2012. The 1,20,000 units will also include 20,000 units of the Corolla Altis, shifted from the first plant to the second plant in the first half of 2012.
Commenting on the expansion Mr. Hiroshi Nakagawa, Managing Director, TKM said "The demand for the Innova and Fortuner has persistently grown in the recent months and consequently the waiting period. The huge demand for the Etios has further provided momentum to expand our production capacity. We will enhance our production capacity to cater to our customers growing demand."
Mr. Sandeep Singh, Deputy Managing Director, Marketing, TKM further added "We recently announced our plans to bring down the waiting period for the Etios, which included enhancing production and deferring the launch of the hatchback Etios Liva.This production expansion will further our aim to bring down the waiting period." Visit http://www.toyotabharat.com for details
Overview of TKM
Company name -- Toyota Kirloskar Motor Private Limited
Managing Director -- President: Hiroshi Nakagawa (TMC)
Established -- October 1997 (start of production: December 1999)
Location --Suburb of Bangalore, Karnataka State
Products -- Corolla Altis, Innova and Fortuner manufactured in India. Camry, Prado, Land Cruiser and Prius imported as CBUs.
Annual production capacity -- Approx. 80,000 units
Equity participation -- TMC: 89%, Kirloskar group: 11%
Number of employees -- Approx. 4,650 (as of end of 2010)
Land area -- Aprox. 432 acres (approx.1,700,000 m2)
Building area -- 74,000 m2
Overview of TKM 2nd Plant
Location -- On the site of Toyota Kirloskar Motor Private Limited (on the outskirts of Bangalore, Karnataka State)
Products -- Etios Sedan and Hatchback Etios Liva (will go on sale in April 2011)
Start of production -- December 2010
Annual production capacity -- 70,000 units.